Project Delay, Contractor’s Failure: MLA Mahesh Tenginkai

Hubballi, August 18: MLA Mahesh Tenginkai has criticized the contractor for failing to complete the flyover construction work within the stipulated deadline.

Speaking to the media after inspecting the project progress on Sunday, he said, “The issue of project delays will be discussed in the meeting of public representatives and various departments scheduled on August 25. A final decision will also be taken on reopening the closed road and resuming bus operations from the central bus stand. Action will be initiated against the contractor company for negligence.”

Officials of the National Highways Authority informed that the delay is mainly due to shortage of laborers. “Workers engage for two or three days and then leave. Even subcontractors are backing out when pressurized, which has further slowed progress. However, about 80% of the critical works have been completed,” they stated.

MLA Tenginkai added that five girders are yet to be installed between Chennamma Circle and Old Court Circle, while six more remain pending near Basava Vana. Out of four portal cap works, two have been completed. It may take another month to finish these along with road and drainage works. Considering the upcoming Ganesh festival, the possibility of temporarily reopening the closed road will be discussed, he said.

He further mentioned that the “Ganesh Mahamandali” has appealed to reopen the blocked bus stand road. Police have also given certain suggestions, which will be reviewed.

 

 