Hubballi Flyover Construction: Gadkari Directs Speed-Up, Approves Additional Funds

New Delhi / Hubballi March,13: Union Minister for Road Transport and Highways, Nitin Gadkari, held a video conference with officials regarding the slow progress of the flyover construction near Kittur Rani Chennamma Circle in Hubballi.
During the meeting, attended by Dharwad MP and Union Minister Pralhad Joshi, Gadkari expressed dissatisfaction over the delays despite central funding. The 3.61 km elevated corridor was approved on August 31, 2020, and construction began on June 4, 2021, with a deadline set for March 20, 2024. However, only 50% of the work has been completed.
The total project cost, initially set at ₹298 crore, has now increased to ₹349.49 crore after an additional ₹51.49 crore was approved. Gadkari assured further financial support if needed and instructed officials to speed up construction, setting strict deadlines for contractors.
The meeting was attended by Dharwad Deputy Commissioner Divya Prabhu, Hubballi-Dharwad Police Commissioner N. Shashikumar, Municipal Commissioner Rudresh Gali, and senior officials from the Public Works Department.